Clackamas River Intake

Lake Oswego’s river intake, also known as the “raw water pump station”, was constructed in 1968, expanded in 1980, and upgraded in 2002.  The facility pumps untreated “raw” water from the Clackamas River to a water treatment plant in West Linn.  From there, treated drinking water is delivered to Lake Oswego residents.

The existing facility has some serious problems:

  • The structure’s concrete floor is decaying and would be costly to repair.
  • Pumps are decades old and suffer from chronic mechanical problems and breakdowns.
  • Electrical and motor cooling systems are inadequate and cannot be upgraded within the existing structure.
  • Reliable pump capacity is only 12 million gallons per day.  Over the past decade, Lake Oswego’s summer peak day demand has regularly exceeded this limit.

Given these problems, upgrading and expanding the existing water intake facility is not a viable option.

A New River Intake Pump Station Under Construction

A new Clackamas River intake pump station, at the western edge of Chief Charles Ames Park, was approved by the Gladstone Planning Commission in 2011. Construction began in June 2013.

The new fish friendly water pump station will deliver water from the Clackamas River to the Lake Oswego Tigard Water Partnership’s water treatment plant in West Linn. The new facility will have the capacity to pump up to 38 million gallons per day (mgd) to serve Tigard and Lake Oswego customers, up from the 16 mgd capacity of the current facility. The new facility has a residential-looking façade, improved fencing, high quality building materials, a drinking fountain and native landscaping. It will be constructed just east of the existing pump station.

The existing facility will be removed. The raw water pipeline that carries untreated water from the intake facility to the water treatment plant in West Linn will also be replaced.

Existing Pump Station
New Design
Existing River Intake Facility New River Intake Design


Project Update

In this video, City of Gladstone Public Works Supervisor, Scott Tabor, explains the benefits that Gladstone will receive by coordinating with the Lake Oswego Tigard Water Partnership team.

Additional Information:

  • May 2013 Meet the Contractor Summary
  • Frequently Asked Question about RIP Construction Handout

How to Get Involved

Click here for upcoming meeting dates.

Sign up to receive email notices.  Mark the ‘Clackamas Water Intake’ as your interest.

Click here to contact us by email.

Call the Water Hotline (503) 697-6502.

Look Ahead: 

You can find regular updates on the Work Underway page.

Field Updates

Friday - May 15, 2015

Curb installation begins on Bellevue Avenue!

Trench and piece of pipe being backfilled.

Preparing for new curbs along Bellevue Avenue.

Gladstone Pipeline and River Intake Construction Update

This update includes construction work in the following areas. Read more for specific information on each location:

  • River Intake Pump Station (RIPS) - demolition begins this summer
  • Exeter Street - pipe installation almost finished
  • Bellevue Avenue - restoration and curb work
  • Jensen Road pathway - pipe installation resumes in late May

Read More

Thursday - April 30, 2015

W. Exeter Street pipe installation progressing well

Crews are currently installing pipe on W. Exeter Street, near Barton Avenue

This update includes construction work in the following areas:

  • River Intake Pump Station (RIPS) - pumps are running, demolition begins this summer
  • W. Exeter Street - pipe installation progressing well
  • Jensen Road Pathway - pipe installation to begin soon
  • Meldrum Bar Park pipeline work - paving work almost complete

Read More

Thursday - April 2, 2015

Pipe installation resumes on West Exeter Street

Finalized architectural stone veneer as part of the entrance gate

Crews have resumed installing pipe on W. Exeter Street, near Bellevue Avenue

Gladstone Pipeline and River Intake Construction Update

This update includes construction work in the following areas. Read below for specific information on each location:

  • River Intake Pump Station (RIPS) - stone veneer complete, pumps are running
  • Microtunnel at Jensen Road pathway - tunneling is underway
  • Meldrum Bar Park pipeline work - paving work has commenced
  • W. Exeter Street - pipe installation in progress

Read More