Previous Entries

Older entries are listed below. You may also browse articles by month.

 
Friday - March 31, 2017

Operator training underway on the new ozone system

Water Treatment Plant Construction Update

On Thursday, the third and final crane that was used for construction was dismantled and removed off-site. As construction comes to a close, more equipment and materials will be leaving the site.

In mid-April, crews expect to remove the large construction trailers currently located on the western corner of the site. Removal is expected to take about a week. A small trailer will be present for the remaining work, near where the carpenters' shed was located on the west side of the site.

Read More

Tuesday - March 28, 2017

Lake Oswego-Tigard Water Partnership inviting neighbors to its garden

by Patrick Malee, The Times - March 26, 2017

In the news...

After four long years of construction, the end is finally in sight this summer for the Lake Oswego-Tigard Water Partnership (LOT) water plant.

To describe the atmosphere of relief at the construction site as "meditative" might be a bit much, but that time will come with some help from the LOT itself. As construction in West Linn's Robinwood neighborhood nears its projected end date in early June, the partnership — a joint endeavor between Tigard and Lake Oswego to provide a source of drinking water for both communities — is working to install a stormwater basin that will double as a "meditation garden" for residents to enjoy while passing through the site.

Open link to external content

Friday - March 17, 2017

Early work on 3/20 for Waluga Reservoir roof pour

Special Construction Update: Waluga Reservoir 1 Roof Replacement

Due to rainy weather and issues with concrete availability, this week's planned concrete pours have been postponed. Weather permitting, crews plan to pour the third quadrant for the roof on Monday, March 20.

To accommodate concrete availability, the City Manager has approved work to begin an hour earlier - the pumper truck will arrive at 6 a.m., with the pour beginning at 6:30 a.m. This will help crews to complete the roof replacement this spring.

Read More

Friday - March 10, 2017

Saturday work at the WR1 site

Special Construction Update: Waluga Reservoir 1 Roof Replacement

Unfortunately, due to recent rainy weather and concrete availability, this week’s final concrete pours have been rescheduled. Tomorrow, Saturday March 11, crews will be pouring the third quadrant for the roof.

To accommodate the Saturday pour, the City Manager has approved work to begin an hour earlier - the pumper truck will arrive at 7 a.m., with the pour beginning at 7:30 a.m. Crews expect to work until 4 p.m. This Saturday work will help crews remain on schedule to complete the roof replacement this spring.

Read More

Thursday - March 9, 2017

Into the final stretch: three months of construction remain at the WTP

Water Treatment Plant Construction Update

Although the weather is persistently dreary, cold and wet, spring is definitely in the air, which means we are embarking on the final three months of construction at the plant!

The following briefly outlines a schedule for major activities that remain. Please note, this is subject to change and several activities are weather dependent:

  • March: ozone system startup and testing, paint and caulk inside ozone building, pour bases for light poles, form curbs, gutters and catch basins, install site walls, build stormwater features, install duct bank and miscellaneous piping

Read More